Retain existing
Continue operating the current system.
- Initial upgrade cost
- $0
- HVAC electricity reduction
- 0% baseline
- Ten-year NPV
- $0 incremental baseline
Do lower operating costs justify a $5 million upgrade?
I linked HVAC electricity estimates to an Excel investment model, comparing three ways to serve the same cooling load over ten years.
Continue operating the current system.
Replace chillers; upgrade plant and controls.
Rebuild chillers; selectively improve equipment.
Source: Executive Investment Summary; Summary!D8:F16. A still has operating and future capital costs. Savings are calculated from assumptions, not measured building performance.
01 / ENGINEERING & METHODOLOGY
The alternatives provide the same assumed cooling service. Equipment performance and control assumptions change the electricity needed to deliver it.
Two assumed 600-ton water-cooled chillers, with a shared load profile and separate auxiliary schedules.
Four chiller load bins plus fan, pump and cooling-tower power estimates.
Apply an illustrative $0.20/kWh tariff, maintenance reductions and recurring analytics costs.
Fans, pumps and tower fans deliver 75.5% of C’s modeled electricity savings. Chiller efficiency alone cannot validate the proposal.
| Component | A Existing | B Full | C Partial |
|---|
Energy!F13:H22; Assumptions!E14. Other electricity is 6,000,000 kWh/year, unchanged. Gas is unchanged and excluded.
Select a component. B replaces chillers and makes broader upgrades; C retains and rebuilds chillers with selective improvements. Both refurbish cooling-tower equipment.
COMPONENT EXPLORER
Adapted from Engineering Analysis, pp. 1–3. Conceptual, not a construction drawing. Water circuits do not mix; the combined pump allowance is counted once. BAS functions are proposed concepts.
Open the full engineering report →tons × load fraction × hours × kW/ton = kWh
The four bins total 1,950,000 ton-hours over 3,000 operating hours: 1,625 equivalent full-load hours.
| Load | Hours | A kW/ton | B | C |
|---|---|---|---|---|
| 25% | 750 | 0.95 | 0.50 | 0.84 |
| 50% | 1,250 | 0.80 | 0.48 | 0.73 |
| 75% | 750 | 0.75 | 0.52 | 0.70 |
| 100% | 250 | 0.72 | 0.585 | 0.70 |
Assumptions!C33:G36. These project bins are not an AHRI IPLV rating. Chiller staging and curves require site evidence.
rated kW × power fraction × annual hours = kWh
B’s fans: 350 × 0.48 × 3,600 = 604,800 kWh/year. The fraction represents average electrical power, not motor speed.
Engineering Analysis, pp. 4–6; Energy!F24:H29. $0.20/kWh is illustrative. Owner retention is 100%; no separate demand-charge savings are added.
02 / FINANCIAL ANALYSIS
I connected the equipment estimates to capital budgets, tax schedules and dated after-tax cash flows. NPV measures the value created relative to retaining the existing system.
Base case8.5% discount rate · ten operating years · USD
Inspect the Excel modelOn small screens, monetary amounts are rounded to millions ($m).
| Investment measure | A Existing | B Full | C Partial |
|---|---|---|---|
| Initial capital | $0 | $5,000,000 | $1,669,000 |
| Annual operating savings Year 1 · pretax | $0 | $399,440 | $190,400 |
| Net present value Primary decision measure | $0 | −$1,754,620 | +$68,531 |
| Internal rate of return Dated XIRR | n/a | −0.38% | 9.44% |
| Simple payback Interpolated · after-tax | n/a | Not within 10 years | 6.51 years |
| Discounted payback Interpolated · at 8.5% | n/a | Not within 10 years | 9.12 years |
B requires $3.331 million more capital than C. Its additional benefits do not earn enough discounted value in the ten-year window. C leads, but its financial cushion is narrow.
Summary!D8:F16; Cash Flow!E89:F94. A’s $0 NPV is an incremental reference, not zero lifetime cost. Payback includes avoided future capital; it is not initial cost divided by first-year savings. C first recovers at Years 7 / 10 with strictly year-end receipts.
Base case · incremental after-tax cash flow · USD millions
Cash Flow!D54:N54, D76:N76; Summary!C51:E61. Year 0 is Dec 31, 2026. Jumps reflect avoided A capital work in Years 3 / 7. C’s Year 5 capital work delays recovery. Terminal value is excluded.
| Year-end | B Full | C Partial |
|---|
The budgets reconcile, but no contractor quotations establish their accuracy. Contingency is 10% of real-property items and is assumed fully spent.
| Budget item | B Full | C Partial |
|---|
03 / SCENARIOS & INVESTMENT RISKS
C leads in the base and optimistic cases. In the downside case, both upgrades have negative NPV. These scenarios test assumptions; they are not probability forecasts.
BASE SCENARIO
Scenarios!D8:G10. Each case changes price, savings, initial cost and the discount rate together. A has zero incremental NPV but still incurs operating and future capital costs.
Calculation consistency is established by the project’s validation work. Building performance and owner economics remain unverified.
Avoided repair and replacement spending materially supports the returns. Confirm equipment condition, service records and the baseline capital plan.
A roughly 4.32% increase in C’s initial cost erases its positive base NPV, other inputs fixed. Obtain comparable bids and clear inclusions.
Measure energy use and substantiate maintenance savings. Verify the avoided tariff, who retains savings, and owner-specific tax treatment.
C / HYPOTHETICAL TEN-YEAR NPV
+$68,531Scenarios!D40:G40. Initial tax basis scales with initial cost; future capital schedules stay fixed. This sensitivity changes two inputs, not the entire financial scenario.
| Cost × / $/kWh | $0.12 | $0.16 | $0.20 | $0.24 | $0.28 |
|---|
Assumptions Validation, pp. 8–9. Each diagnostic holds other inputs fixed. These are not proposed changes to the baseline.
The supplied Step 3 report documents 94 independent comparisons. Step 2 records control corrections to the original model. Those are historical project checks; they do not establish site savings or investment readiness.
Read the assumptions validation →04 / INVESTMENT RECOMMENDATION
Partial upgrade offers the strongest base-case NPV and uses less capital. Its small surplus and late discounted recovery leave limited room for error.
Better ten-year value. B’s additional $3.331m is not justified by the modeled incremental benefits.
A modest return, not a robust approval case. C’s 9.44% XIRR barely exceeds the 8.5% discount rate; discounted payback is 9.12 years.
This independent hypothetical study supports further investigation. It does not approve either upgrade or establish lifetime performance beyond the ten-year planning window.